preparing to dig the hole by first digging a bunch of other smaller holes

August 10 - 19 2026

The construction crew has apparently decided that before they can dig a giant hole in the ground, they need to have a very serious conversation with everything already living underneath it.


The current phase appears to be underground utility and infrastructure work. There is drilling going on along the street, specialized equipment parked in the future excavation area, and a collection of large precast concrete structures stacked along the upper-right side of the site.


Those mysterious concrete boxes look like utility/manhole or drainage structures. Several have large circular openings on top and additional openings on the sides and look exactly like the sort of things that eventually disappear underground and become everybody's problem when something needs to be repaired 20 years from now.


Imagine trying to dig a deep basement while discovering halfway down that there is a water line, sewer, storm drain, electrical conduit, or other piece of municipal infrastructure exactly where your giant hole is supposed to go. Much easier to sort that out before the excavators arrive and turn the entire site into a canyon!


Well, That Escalated Quickly

July 27 - Aug 7, 2026

The grapple had its fun, and now it was time to clean up the mess!


Over the next week and a half, the demolition operation moved quickly. What had been a standing building at Fifth and Lavaca was systematically taken apart, hauled away, and sorted.


And honestly, one of the most impressive parts wasn't the destruction. It was the precision.


Watching a machine that enormous reach into a building and pull out exactly what it wanted was almost surgical. The equipment looked capable of demolishing the entire block in one afternoon, yet the operators worked with remarkable control, grabbing, lifting, separating, and placing material with surprising accuracy.


Big machines. Tiny margins. Piece by piece, the building disappeared.


And the crews weren't simply tossing everything into one giant pile. As the structure came apart, materials were separated and sorted. Metal going one direction, stone and concrete another, with plastics and other materials being pulled into their own streams.


What looked from the street like controlled chaos was actually a pretty organized operation and by August 7, the dirt was all that was left.


Nom Nom Nom Goes the Grapple

July 23, 2026

Well, that's one way to make an entrance! After years of planning, the demolition equipment has arrived and the grapple is hungry!!


Nom.

A chunk of the old building disappears.


Nom nom.

Another one bites the dust.


The machinery is beginning to take apart what has been standing at Fifth and Lavaca for decades. The buildings that once held businesses, bars, music, and nightlife are now being reduced piece by piece as the site makes way for what comes next.


It is a little surreal watching it happen. For years, the future of this corner existed mostly in documents: site plans, permit applications, revisions, approvals, and renderings.


Now you can hear it. And you can definitely see it.


The grapple doesn't care about the permitting history. It doesn't care how many meetings happened or how many PDFs were submitted. It has one job.


Nom nom nom.


The old corner is coming down. And for the first time, the future hotel isn't just something you can find in a City of Austin database.


It's happening right in front of us.


Source: Austin Business Journal report "Demolition imminent for downtown Austin site eyed for Hilton hotel dated July 23, 2026

Alright, Austin. Here We Go

July 21, 2026

The paperwork has been piling up for years, now the barricades are piling up on Fifth Street.


The perimeter around the site is going up, fencing is appearing, and the familiar footprint of 209 and 213 West Fifth Street is beginning to disappear behind construction barriers.


For anyone driving through downtown, this is the moment the project becomes impossible to ignore.


Fifth Street has officially entered its “please merge, but also somehow don't hit anything” era. Lanes get narrower. Traffic gets confused. Someone will inevitably decide that a construction barrier is merely a suggestion.


But behind the fencing, something much bigger is happening.


The site is being prepared for demolition and the construction that will follow. After years of plans, permits, reviews, ownership changes, and paperwork, the project is finally beginning to physically change the corner.


This is the first real sign that the old site is about to become a construction site! If you are driving by over the next few days, take a good look because the view is about to change.


Building Permits Issued

2026

The master building permit 2024-104678 BP was issued on January 21, 2026. This permit represented the formal construction authorization for the new hotel shell and carried forward the approved building package for 415 Lavaca Street.


The master permit covered the new construction of:

  • 30-story 336,852 project,
  • hotel shell,
  • basement,
  • mechanical penthouse,
  • restaurant space,
  • and related building systems.


With the master permit issued, the project had completed the regulatory approval process and reached the final stage before physical construction.


In addition, the project was organized through a series of related permit applications covering the future hotel program, including:

  • basement areas,
  • arrival lobby and common areas,
  • restaurants and food service spaces,
  • guestrooms,
  • meeting spaces,
  • ballroom areas,
  • fitness amenities,
  • and upper-floor hotel spaces.


These permits were issued on July 29, 2026, after demolition started.

Source: Permit filings at austintx.gov


Source: 2023-074810PR filing at austintx.gov

Keeping The Approval Alive

July 2025

By mid-2025, the project had completed the major approval process, but construction had not yet begun.


The approved permit pathway remained active; however, as time passed, the project approached the expiration requirements associated with an approved permit application.


On July 28, 2025, an extension request was submitted for Permit Review application 2023-074810 PR. The reason provided was that “building owner needs more time before starting construction”


This brief statement provides an important insight into the project's timeline. The timing of the six-month extension suggests that it served two purposes: 1) needing more time before starting construction, and 2) preserving the approval while the ownership team finalized the transition from approved plans into an issued construction permit.


From Site Plan Approval to Building Permit Phase

2024

After nearly two years of coordinated review and revisions, the project reached a major milestone in 2024: the transition from site planning into the building permit phase.


The first major milestone was the approval of the site plan on June 25, 2024 (expiring June 25, 2027). This approval confirmed the approval of a 30-story hotel with related uses for a total of 11,813 sf impervious cover, including:

  • site layout,
  • building placement,
  • circulation,
  • civil improvements,
  • utilities,
  • drainage,
  • and other site-related requirements.


With the site plan approved, the project continued through the building review process for the structure itself. The associated Permit Review application 2023-074810 PR, originally submitted on June 13, 2023, completed the City's technical review process and reached Approved and Released status on August 16, 2024.


That milestone represented the approval of the building design package for the proposed:

  • 30-story hotel,
  • basement,
  • mechanical penthouse,
  • restaurant space,
  • and related improvements.


Following the PR approval, the project transitioned into the building permit phase. On August 16, 2024, the master building permit application 2024-104678 BP was filed.


The permit package carried forward the approved construction documents and organized the project into a master permit with 36 related building applications covering the future hotel components.


Together, the approved site plan, released permit review, and creation of the master building permit established the final regulatory framework for the project. The redevelopment had completed the major approval process and was positioned to move toward construction.

Source: 2023-074810PR filing at austintx.gov


Source: Historic Landmark Commission 2022 Meetings documents dated May 4, 2022.

The Historic Buildings Prepare For Demolition

2022 - Nov 2023

Before a new hotel could rise at Fifth and Lavaca, the existing buildings had to go through their own review process.


As redevelopment plans moved forward, the City of Austin began documenting the existing properties at 209 and 213 West Fifth Street through the historic review process. The review created an official record of the buildings, their architecture, and their evolution before demolition could proceed.


On May 4, 2022, the Historic Landmark Commission reviewed the proposed demolition of the two commercial buildings as part of DA-2022-011968 / GF-2022-050219. The properties were identified as circa 1918 and circa 1919 commercial buildings, and the City "encouraged rehabilitation and adaptive reuse, then relocation over demolition, but release the permit upon completion of a City of Austin Documentation Package."


The documentation preserved the history of the corner, recording buildings that had evolved alongside downtown Austin for more than a century.


Following the completion of the required review process and site plan determination date of June 1, 2023, demolition permits were filed for each parcel September 21, 2023. Associated building permits were filed shortly thereafter, with all building and demolition permits issued by November 7, 2023. All expire January 19, 2027.


213 West Fifth Street

Demolition Permit: 2023-123081 PR

Associated Building Permit: 2023-138384 BP

DA-2023-0486


The permit authorized demolition of the 5,888-square-foot development at 213 West Fifth Street, circa 1931. The building was best known in recent decades as a longtime entertainment venue, including its years associated with Antone’s and later nightlife uses.


209 West Fifth Street

Demolition Permit: 2023-122915 PR

Associated Building Permit: 2023-142563 BP

DA-2023-040144


The permit authorized total demolition of the 5,888-square-foot bar building at 209 West Fifth Street, circa 1985. The property carried a long commercial history, including earlier twentieth-century uses and later nightlife activity that contributed to the character of the block.


With both demolition permits approved, the site was cleared for the next phase of redevelopment: transforming the historic Fifth and Lavaca corner into a new downtown hospitality project.


Designing the Building: Coordinated Review Begins

2023

With the site plan process underway, the project entered a period of continued refinement as both the site design and building plans evolved together.


The site plan review for SP-2022-0518C continued through multiple rounds of revisions as the project team refined the proposed redevelopment of 415 Lavaca Street as the design continued to develop through the City's review process.


The project was presented on April 24, 2023 through the Urban Design Guidelines (UDG) review process. This provided an opportunity to evaluate how the proposed development responded to the surrounding downtown context, including design, scale, and urban integration.


On June 13, 2023, the project continued to advance with the submission of the major building Permit Review application 2023-074810 PR. This application represented the formal review of the proposed new hotel at 415 Lavaca Street.


The proposed project included:

  • 30-story hotel tower,
  • basement,
  • mechanical penthouse,
  • restaurant space,
  • hotel lounge,
  • and 36 related permit applications.


The project was divided into multiple coordinated applications covering the major components of the future building, allowing the City and project team to review the complex development in an organized manner. Concurrently, the project continued through additional planning discussions, including the June 13, 2023 density bonus meeting, as the team refined the final development program.


By July 20, 2023, the revised site plan submission reflected the updated hotel concept, including:

  • approximately 483 guestrooms,
  • approximately 10,000 square feet of fine dining restaurant space,
  • hotel lounge areas,
  • and associated site improvements.

Source: UDG Presentation dated May 24, 2023


Source: SP-2022-0518C Filing at austintx.gov

The Permitting Process Begins

2022

The first project filings appeared in early 2022, beginning the formal review process for the redevelopment of 415 Lavaca Street, covering the combined project area associated with:

209 West Fifth Street

213 West Fifth Street

 

Before a new building could take shape, the project team had to establish how the site would be transformed, documented, and integrated into the surrounding downtown block. The team began coordinating several pieces of the redevelopment process, including:

  • redevelopment plans,
  • historic review requirements,
  • site design,
  • and the approvals needed to replace the existing commercial buildings with a new hospitality project.


In October 2022, Kimley-Horn submitted Site Plan SP-2022-0518C. The site plan process to answer whether the project could physically and legally happen on this site. Unlike a building permit, which focuses on constructing the building itself, a site plan establishes the framework for the entire development. It coordinates the pieces needed to transform an existing property into a future project, including:

  • site layout,
  • building placement,
  • circulation,
  • civil improvements,
  • utilities,
  • drainage,
  • and other site-related requirements.


The site plan would continue through review and revisions as the design evolved toward the final hotel concept.


Securing the Land

2016 - 2022

The redevelopment of Fifth and Lavaca did not begin with the first hotel drawings. The groundwork was laid years earlier through a series of ownership changes and agreements that gradually connected two historically separate properties.


In February 2015, 213 Holdings LLC acquired 213 West Fifth Street from HOMY LTD. The acquisition occurred during a period when the property was transitioning away from the Antone’s era and toward its next identity as an entertainment venue.


The following year, a critical connection was established. On December 15, 2016, 209 West 5th LLC, the longtime owner of the adjacent 209 West Fifth Street property, executed a lease with 213 Holdings LLC. While the two parcels remained separately owned, the agreement created a formal relationship between them for the first time, allowing the adjoining properties to function together.


This arrangement coincided with the arrival of the Spin era, when the corner was reinvented as a sports and entertainment destination. The physical connection created during this period became the foundation for the property's future redevelopment.


In November 2017, ownership of 213 West Fifth Street transitioned again when MVA-213 LLC, associated with Robert Hersch and Mastodon Ventures, assumed ownership from 213 Holdings LLC. The lease relationship connecting the adjoining properties continued as part of the property's development structure.


After years of assembling the site, MVA-213 LLC transitioned the property into a new ownership structure in 2022. PSOF Austin Hotel Owner LLC was formed (April 2022) as the ownership entity for the planned Hilton Dual Brand Hotel, bringing the assembled interests at Fifth and Lavaca into a hospitality development platform associated with Peachtree Group.